TIME SCHEDULE FOR GRANT OF PERMANENT/TEMPORARY ELECTRICITY CONNECTION (NEW/ ADDITIONAL LOAD/ TRANSFER OF CONNECTIONS) UPTO 100KW LOAD:

Permanent Connection :

·        Acknowledgement of receipt of application form with requisite documents- On the spot on the same day

·        Scrutiny of application form and information about deficiencies – within 7 days.

·        Sanction, Deposit of charges and release to Zone- Within 10 days

·        Energisation and installation of meter and service line subject to technical feasibility – Within 20 days from the date of deposit of charges

In case of delay in grant of connection the prospective applicants should contact the concerned Superintending Engineer of the Circle, in case connection is not energized within one month and Addl. Chief Engineer in case the connection is not energized within 3 months. The reasons for any delay beyond this period shall be investigated by Chief Engineer concerned and report submitted to Chairman.

Temporary Connection for marriages, functions etc.

·        Sanction, Deposit of charges, and release to Zone for meter installation – Within  7 days

·        Installation of meter and energisation subject to technical feasibility – Within 7 days.

Citizen's rights with respect to DVB

Lets unite to gear up the Govt machinery                      

Home        Objectives        Strategy        Income Tax Refunds        Citizens' Charter
Reactions        Future Plans         Join Parivartan        Feedback

Address : Parivartan, 5B, Navkala Apartments, 14, I P Extension, Patparganj, New Delhi - 92

Tel : 2727430

E-mail Address : parivartan_india@hotmail.com